The SR 31 Fix Finishing in 2027 Isn't the Stretch That Leads Out of River Hall

"It's very quiet until the builders came along, and now it's pretty noisy."

That's how longtime Alva resident Sandy Mae described her corner of the county in a WINK News report this spring, and anyone who leaves River Hall Country Club by way of Palm Beach Boulevard has heard some version of the same line over coffee at Town Hall. The complaint usually lands on the same target: the State Road 31 widening project that's been in local headlines since 2023. The SR 31 corridor includes a stretch separate from the one River Hall residents drive most often.

Two Projects Share a Name and Nothing Else

State Road 31 runs from the Wilson Pigott Bridge over the Caloosahatchee north through Babcock Ranch toward Charlotte County, and FDOT has split the corridor into two separate construction jobs that happen to share a route number.

The first phase, the one generating the "SR 31 is almost done" news, runs 4.91 miles from Bayshore Road up to Lake Babcock Drive. Kitson & Partners, the developer behind Babcock Ranch, fully funded the $85 million cost themselves. Work started early. That new four-lane road, with roundabouts at Shirley Lane, Fox Hill Road and Lake Babcock Drive, is on track to open in May 2027. It's a real project with a real date. It's also entirely north of the stretch that matters for River Hall.

River Hall's main entrance sits at River Hall Parkway and SR-80, about ten miles east of I-75's exit 141, right where SR-80 meets the southern end of SR-31. That southern 1.4-mile segment, from Bayshore Road down to Palm Beach Boulevard, is a separate, second phase. It's funded by FDOT rather than a private developer, and as of late July 2026 the department was still expecting to accept bids, with construction slated to begin sometime in 2027. No completion date has been published for it yet. So when a neighbor mentions the SR 31 project wrapping up next spring, they're talking about Babcock Ranch's commute, not River Hall's.

The Drawbridge That Isn't Going Anywhere Yet

The reason phase two matters more to River Hall than phase one is the Wilson Pigott Bridge, the two-lane drawbridge built in 1960 that still raises for boat traffic on the Caloosahatchee and stacks cars on both banks when it does. The plan calls for replacing it with a high-span fixed bridge offering 57 feet of vertical clearance, more than double the current structure's 27 feet, which would end the drawbridge waits entirely. That bridge is part of phase two. It has not started.

In a North Fort Myers Neighbor report, Syd Kitson, whose company funded the first phase, put the underlying problem plainly: "the bridge has failed because the traffic has increased." He was talking about regional truck traffic from mines up toward Lakeland as much as local growth, but the effect on River Hall's daily commute is the same either way. The fix for that specific problem is still in the bidding stage, a year or more behind the project everyone keeps reading about.

The Growth Pushing the Timeline

Part of why this corridor carries so much traffic pressure right now is that Alva and neighboring Olga are absorbing more rezoning requests than at almost any point in the area's history, and both of the current fights sit close enough to River Hall to matter.

The larger one involves 561 acres of ranchland where D.R. Horton has proposed 737 single-family homes. Lee County gave the applicant an extension to June 30, 2026 to submit additional rezoning information after reports the builder had stepped back from the deal, and "Keep Alva Rural" yard signs went up around the community in response. As of the county's development review list dated July 5, 2026, the case was still open, requesting a shift from Agricultural to Residential Planned Development zoning.

A second, smaller case moved faster. Alva Inc., the local advocacy group pushing back on rapid rezoning, flagged a Lee County Board of County Commissioners hearing for September 2, 2026 on the Caloosa 80 comprehensive plan amendment, which would redesignate roughly 92 of a 192-acre tract near Hickey Creek Mitigation Park from Rural to Sub-Outlying Suburban, potentially clearing the way for about 720 homes and 30,000 square feet of commercial space just off Palm Beach Boulevard. That hearing happened last month. Every one of those future rooftops, if approved, adds trips to the same SR-31 corridor that's still waiting on its bridge fix.

Here's the corridor as it stands right now:

  • Phase one (Bayshore Road to Lake Babcock Drive): $85 million, funded by Kitson & Partners, opening May 2027, with roundabouts at Shirley Lane, Fox Hill Road and Lake Babcock Drive.
  • Phase two (Bayshore Road to SR 80, including the Wilson Pigott Bridge): funded by FDOT, bids expected in the near term as of July 2026, construction to begin sometime in 2027, no completion date announced.
  • The 561-acre rezoning case: extension deadline was June 30, 2026; still listed as an open review item as of early July.
  • The Caloosa 80 hearing: heard by county commissioners September 2, 2026, covering roughly 92 of 192 acres near Hickey Creek Mitigation Park for up to about 720 homes.
  • River Hall's own gate fix: the Town Hall Amenity Campus golf cart gate went operational August 28, 2026, giving residents a way to reach the pool and fitness center without merging onto Palm Beach Boulevard at all.

That last item is the one piece of genuinely finished infrastructure on this list, and it's worth sitting with for a second. While the county-level fix sits a year or more out, River Hall's own HOA solved a smaller version of the same access problem inside the gates in a matter of months.

What's Already Working Around the Club

None of the road news has slowed down what's actually easy about living in River Hall. The Caloosa Bar & Grill and the Bunker Bar, both on the golf course side of the community, remain the simplest answer for a weeknight dinner that doesn't involve SR-31 at all. Neighbors organizing on Nextdoor still trade recommendations for Parent Night at il Primos, the kind of small, recurring local ritual that keeps happening regardless of what FDOT's bid schedule looks like. For anyone wanting a change of scenery without joining the crawl toward Fort Myers, Alva Saloon sits close enough to make an easy out-and-back evening.

The point isn't that construction is ruining anything. It's that the corridor everyone talks about as one project is actually two, moving at two different speeds, and only one of them touches the drive River Hall residents make most often. FDOT's project pages for both segments are public and update as bids and schedules move.

If you want a local update on what's finished and what's still in a bid packet along this stretch of Alva, the Batey Westerlund Team tracks this corridor the way locals do, mile marker by mile marker. Reach out to Ryan Batey anytime you want a local perspective on this corridor.