When does Pine Ridge Road stop being a construction zone? For anyone who lives at Kensington Golf and Country Club, 2700 Pine Ridge Road, two agencies give two different answers. The Florida Department of Transportation expects to finish the I-75 interchange in mid-2027. Collier County's next project, a redesign of the Pine Ridge and Livingston Road intersection, could begin construction in summer 2027 and last about 18 months. On that schedule, the work doesn't wrap up next year. It moves west to Livingston and could last into late 2028 or early 2029.
The interchange part is almost finished. The Livingston part is still being designed, and it's the one that changes how you get in and out of the corner closest to home.
One More Weekend Under I-75
FDOT's last scheduled disruption at exit 107 is coming soon. The project page says crews will install signs on the overhead trusses in late October or early November. That work requires ramp closures and a full weekend closure of Pine Ridge Road under I-75 in both directions, for drivers, pedestrians and cyclists. The page adds that "more details will be provided as schedules are finalized."
The most recent full closure is the best guide to what the weekend will feel like. Gulf Coast News reported that the closure starting Friday, Sept. 25 ran from 11 p.m. Friday to 6 a.m. Monday, with these detours:
- Southbound I-75 traffic headed for eastbound Pine Ridge Road used Immokalee Road and Logan Boulevard.
- Northbound I-75 traffic headed for westbound Pine Ridge Road used Golden Gate Parkway and Livingston Road.
- Drivers on Pine Ridge Road who needed to cross under the interstate got on I-75 and made a U-turn at the Immokalee Road or Golden Gate Parkway exit.
FDOT hasn't announced a detour for the sign-truss weekend yet, so treat September's routes as a likely pattern, not the official plan. The second route matters most locally. It sends northbound interstate traffic up Livingston Road, the same intersection the county plans to rebuild next.
Away from that weekend, FDOT says drivers should expect occasional overnight lane closures on Pine Ridge Road from 7 p.m. to 7 a.m. and ramp closures from 8 p.m. to 6 a.m. Those windows mostly miss the drive to dinner and back. They don't miss a late return from Southwest Florida International Airport.
What's Left at Exit 107
The big change at the interchange happened in the spring. FDOT planned to open the diverging diamond on Monday, June 1. Florida Weekly reported that it opened a day early, on Sunday, May 31, so it could serve as a detour after a crash on southbound I-75 between the Pine Ridge and Golden Gate Parkway exits. It's the first diverging diamond in Collier County.
That opening finished the new traffic pattern, not the project. Florida Weekly listed what was still to come: sidewalks, barrier walls, pond excavation, permanent signs and signals, lighting, paving, striping and sod. FDOT's current project notes show crews on permanent signals, signal timing, sign placement, wrong-way vehicle detection and sod. That's finishing work. The roughly $27.5 million rebuild started its construction phase in early 2025 and is now mostly tuning signals and placing signs.
Retiming the signals is the part drivers will notice most. FDOT says the design cuts delay on Pine Ridge Road and reduces conflict points, and it adds new signals at the ramps plus walking and biking routes through the interchange. Once the signals are tuned, the interchange should stop being the slowest point between Kensington and the interstate. That's when the county's project starts.
The Handoff, in Order
Side by side, the two schedules overlap more than they line up end to end.
| When | What happens | Agency |
|---|---|---|
| Early 2025 | Interchange construction phase begins | FDOT |
| May 31, 2026 | Diverging diamond opens, one day ahead of plan | FDOT |
| June 18, 2026 | Public meeting on 60% design for Pine Ridge at Livingston | Collier County |
| Late Oct. or early Nov. 2026 | Weekend closure under I-75 for sign trusses | FDOT |
| End of 2026 | Corridor design completion expected | Collier County |
| Mid-2027 | Interchange final completion estimated | FDOT |
| Summer 2027 | Corridor construction could begin, about 18 months | Collier County |
Both of the county's dates are written as possibilities. The handout says construction is "potentially commencing" in summer 2027, and neither the June release nor the handout gives a cost or says whether construction is funded. If that start date holds, FDOT's finishing work and the county's first work at Livingston could happen in the same season.
What the Jughandle Changes at Livingston
Collier County's Pine Ridge Road Corridor Improvements project runs along Pine Ridge Road from Livingston Road to Lawson Way. The main piece is a jughandle. That's a separate turning road that pulls certain turns out of the main intersection. In this design, Livingston Road's left turns and Pine Ridge Road's eastbound right turn would go onto the jughandle. The county says removing those turns gives Pine Ridge Road traffic more green time at the signal.
The 60% design handout shows where those turns would split off. For northbound Livingston drivers turning left, it's about 600 feet south of Pine Ridge. For eastbound Pine Ridge drivers turning right, it's about 420 feet west of Livingston. If you take those turns often, the change is simple to describe. The turn no longer happens at the light. It happens a short distance before it.
The rest of the package covers the side roads around the intersection:
- A second left-turn lane from Kramer Drive onto Pine Ridge Road
- A new Livingston Road left-turn lane into Meridian Plaza
- Longer turn lanes on Pine Ridge Road, plus a longer turn lane at Marquesa Plaza
- Resurfacing of Pine Ridge Road, Livingston Road, Kramer Drive and Whippoorwill Lane within the project limits
- A sidewalk from Whippoorwill Lane to Lawson Way
The sidewalk is what ties the two projects together. The handout says it connects to the Napa Boulevard sidewalk built as part of FDOT's interchange work. Taken together, the interchange's new walking and biking routes and the county's new sidewalk segment are meant to fill gaps in the walking route along this part of Pine Ridge Road.
The full design exhibits for Pine Ridge Road and Livingston Road from the June 18 meeting are posted on the county's transportation engineering projects page. Dennis McCoy, P.E., is listed as project manager. The exhibits are the only place to see exactly where the jughandle sits relative to the plazas and side streets you use, and design is supposed to be final by year-end.
The Sunday Stop at the Same Corner
The intersection getting rebuilt is also home to one of the area's steadiest weekly routines. The Pine Ridge Road Farmers Market runs year-round on Sundays from 9 a.m. to 1 p.m. at Marquesa Plaza, 3370 Pine Ridge Road, at Pine Ridge and Livingston. Vendors sell local produce, baked goods, flowers, prepared foods, crafts and gifts.
That address explains why the county's lane list mentions Marquesa Plaza by name. The longer turn lane into the plaza is part of the corridor design. So is the new left-turn lane on Livingston into Meridian Plaza. Over roughly 18 months of work, the same corner where you buy Sunday produce is where the lanes will shift, and when it's done, getting into both shopping centers should be simpler.
For the coming weeks, the steps are short. Watch the FDOT project page for exit 107, which also has an email signup for construction updates, for the exact sign-truss weekend. If that weekend includes a Sunday, the market at Marquesa Plaza is west of the closure, so you can get there without crossing under I-75.
The Batey Westerlund Team at Ryan Batey follows projects like the Pine Ridge corridor because road schedules affect how a neighborhood shows to buyers and how quickly a sale comes together. If you're thinking about selling at Kensington between now and the end of the Livingston work, we can talk through how the construction calendar might fit your timing, starting with where your home's value stands today. Get Your Instant Home Valuation.